New club update!

The completion date of the new facility has moved by one week to 14 February 2019. Over the next few weeks the following will be the focus of work:

  • Finishing tennis courts pour.
  • Retaining walls
  • Roof sheets
  • Steel painted
  • Install structural steel
  • Complete decking
  • Build walls